Locating And Marking Practices…From The CGA Best Practices 15.0

Understanding the Marks: Locating and Marking Practices

Operator markings of facilities include the following:

• The appropriate color for their facility type
• Their company identifier (name, initials, or abbreviation) when other companies are using the same color
• The total number of facilities and the width of each facility
• A description of the facility (HP, FO, STL, etc).

Use paint, flags, stakes, whiskers, or a combination to identify the operator’s facility(s) at or near an excavation site.

Illustration 1Illustration 1

  1. Marks in the appropriate color are approximately 12 in. to 18 in. long and 1 in. wide, spaced approximately 4 ft to 50 ft apart. When marking facilities, the operator considers the type of facility being located, the terrain of the land, the type of excavation being done, and the method required to adequately mark the facilities for the excavator. (Illustration 1)

Illustration 2a1
Illustration 2a1

  1. The following marking examples illustrate how an operator may choose to mark their subsurface installations:

Illustration 2a2
Illustration 2a2

a. Single Facility Marking: Used to mark a single facility. This can be done in one of two ways:

Illustration 2b
Illustration 2b

• placing the marks over the approximate center of the facility. (Illustration 2a1) or

Illustration 2c
Illustration 2c

• placing the marks over the approximate outside edges of the facility with a line connecting the two horizontal lines (in the form of an H) to indicate there is only one facility. (Illustration 2a2)

Illustration 2d
Illustration 2d

These examples indicate an operator’s 12 in. facility. When a facility can be located or toned separately from other facilities of the same type, it is marked as a single facility.41

b. Multiple Facility Marking: Used to mark multiple facilities of the same type (e.g., electric), where the separation does not allow for a separate tone for each facility, but the number and width of the facilities is known. Marks are placed over the approximate center of the facilities and indicate the number and width of the facilities. Example: four plastic facilities that are 4 in. in diameter (4/4” PLA). (Illustration 2b)

c. Conduit Marking: Used for any locatable facility being carried inside conduits or ducts. The marks indicating the outer extremities denote the actual located edges of the facilities being represented. Example: four plastic conduits that are 4 in. in diameter (4/4” PLA), and the marks are 16 in. apart, indicating the actual left and right edges of the facilities. (Illustration 2c)

d. Corridor Marking: Used to mark multiple facilities of the same type (e.g., electric), bundled or intertwined in the same trench, where the total number of facilities is not readily known (operator has no record on file for the number of facilities). Marks are placed over the approximate center of the facilities and indicate the width of the corridor. The width of the corridor is the distance between the actual located outside edges of the combined facilities. Example: a 12 in. corridor (12” CDR). (Illustration 2d)

Illustration 3a
Illustration 3a

  1. Changes in direction and lateral connections are clearly indicated at the point where the change in direction or connection occurs, with an arrow indicating the path of the facility. A radius is indicated with marks describing the arc. When providing offset markings (paint or stakes), show the direction of the facility and distance to the facility from the markings. Example: radius (Illustration 3a)

Illustration 3b
Illustration 3b

Example: lateral connection (Illustration 3b)

Illustration 3c
Illustration 3c

Example: painted offset (off) (Illustration 3c)

Illustration 3d
Illustration 3d

Example: staked offset (off) (Illustration 3d)

  1. An operator’s identifier (name, abbreviation, or initials) is placed at the beginning and at the end of the proposed work. In addition, subsequent operators using the same color mark their company identifier at all points where their facility crosses another operator’s facility using the same color. Reduce the separation of excavation marks to a length that can reasonably be seen by the operator’s locators when the terrain at an excavation site warrants. Examples:
  1. Information regarding the size and composition of the facility is marked at an appropriate frequency. Examples: the number of ducts in a multi-duct structure, width of a pipeline, and whether it is steel, plastic, cable, etc.
  1. Facilities installed in a casing are identified as such. Examples: 6 in. plastic in 12 in. steel and fiber optic in 4 in. steel.
  1. Structures such as vaults, inlets, and lift stations that are physically larger than obvious surface indications are marked so as to define the parameters of the structure. Example:
  1. Termination points or dead ends are indicated as such. Example:
  1. When there is “No Conflict” with the excavation, complete one or more of the following:

• Operators of a single type of facility (e.g., TELCO) mark the area “NO” followed by the appropriate company identifier in the matching APWA color code for that facility. Example: NO TELCO

• Operators of multiple facilities mark the area “NO” followed by the appropriate company identifier in the matching APWA color code for that facility with a slash and the abbreviation for the type of facility for which there is “No Conflict.” Example: NO GASCO/G/D illustrates that GASCO has no gas distribution facilities at this excavation site. The following abbreviations are used when appropriate: /G/D (gas distribution); /G/T (gas transmission); /E/D (electric distribution); /E/T (electric transmission).

• Place a clear plastic (translucent) flag that states “No Conflict” in lettering matching the APWA color code of the facility that is not in conflict. Include on the flag the operator’s identifier, phone number, a place to write the locate ticket number, and date. Operators of multiple facilities indicate on the flag which facilities are in “No Conflict” with the excavation (see the previous example).

• If it can be determined through maps or records that the proposed excavation is obviously not in conflict with their facility, the locator or operator of the facility may notify the excavator of “No Conflict” by phone, fax, or e-mail, or through the One Call Center, where electronic positive response is used. Operators of multiple facilities indicate a “No Conflict” for each facility (see the previous examples).

• Place “No Conflict” markings or flags in a location that can be observed by the excavator and/or notify the excavator by phone, fax, or e-mail that there is “No Conflict” with your facilities. When the excavation is delineated by the use of white markings, place “No Conflict” markings or flags in or as near as practicable to the delineated area.

Caution: Allow adequate space for all facility mark-outs.

“No Conflict” indicates that the operator verifying the “No Conflict” has no facilities within the scope of the delineation; or when there is no delineation, there are no facilities within the work area as described on the locate ticket. Example:

Guide for Abbreviation Use

Follow these guidelines when placing abbreviations in the field:

• Place the Company Identifier at the top or at the left of the abbreviations.

• Place the abbreviations in the following order: Company Identifier / Facility Identifier / Underground Construction Descriptions / Infrastructure Material. Example: TELCO/TEL/FO/PLA indicates that TELCO has a telecommunication fiber optic line in a single plastic conduit. The use of the abbreviation /TEL is not necessary, because the orange marking would indicate that the facility was a communication line; but its use is optional.

• To omit one or more of the abbreviation types, use the order described above but omit the slash and abbreviation that does not apply. Example: to omit /TEL, the result would be TELCO/FO/PLA.

COLOR CODE IDENTIFIERS

Proposed Excavation

Temporary Survey Markings

Electric Power Lines, Cables, Conduit, and Lighting Cables

Gas, Oil, Steam, Petroleum, or Gaseous Materials

Communication, Alarm or Signal Line, Cables, or Conduit

Potable Water

Reclaimed Water, Irrigation, and Slurry Lines

Sewers and Drain Lines

TAKEN FROM CGA BEST PRACTICES 15.0